Project Information
- Status Completed
- Location Türkiye
- Year Nisan 2017
- Client Sönmez Çimento
Contact Us
Scope of Work
*9,842 m² jetty and dolphin construction
*Driving of 391 pcs Ø1219.2 mm, t=14 mm (27–32 m) steel pipe piles with marine equipment
*Installation of fenders, bollards, rings and crane rails
*25,083 m² of formwork
*2,480 tons of rebar installation
*30,377 m³ of concrete pouring