Kabatas Transfer Center Project

Kabatas Transfer Center Project

Project Gallery

Project Information

  • Status Completed
  • Location İstanbul, Türkiye
  • Year 28 Kasım 2016
  • Client İstanbul Üstyapı İnşaat ve Ticaret A.Ş.

Contact Us

Scope of Work

*Piled quay construction:

Driving of 339 pcs Ø914.4 mm, t=12 mm steel pipe piles

  • Rock drilling with Soilmec RT3-ST
  • All reinforced concrete works for cap beams and slabs for the 580 m long quay structure
  • Precast element placement
  • 4,000 tons of rebar work
  • 10,500 m³ concrete pouring

*Piled jetty construction:

Driving of 266 pcs Ø1117.6 mm, t=18 mm steel pipe piles

  • Rock drilling with Wirth PBA 818
  • All reinforced concrete works for three separate jetties for City Lines ferries, sea buses and passenger boats
  • Precast element placement
  • 1,500 tons of rebar work
  • 8,000 m³ concrete pouring

*Ground improvement works:

  • 13,000 pcs Ø600 mm jet-grout columns of varying lengths in the sea
  • Driving of 36 pcs Ø914.4 mm, t=12 mm transition slab support piles in the quay area